Repowering Study for the Northport and Port Jefferson Power Stations: Answers to Questions Received
The following are answers to questions received regarding the Repowering Study RFP.
Question 1: Has the
RFP for the electric rate impact study been issued? If so
can we receive a copy? Question 2: Also, our Integrated
Electric Resource Planning practice resides within our T&D
Strategy group. We develop several such plans for utilities
each year. Has the RFP for the Integrated Electric Resource
Plan been issued? If so can we receive a copy?
Answer to Questions 1/2: The electric rate impact
analysis and the integrated resource planning work will be
performed in house. There are no additional RFPs planned
regarding the re-powering study.
Question 3: Due to the
significant effort in preparing a quality proposal for you
with the cost information that is required, and to allow for
the holiday period, we would like to request that Keyspan
consider an extension of the bid due date for two weeks to
January 24th.
Answer to Question 3: The Jan 10th date needs to be
maintained to support LIPA schedule requirements.
Question 4: What is the level of accuracy for capital
cost and operating cost estimates required for the Phase I
and II studies?
Answer to Question 4: Phase I is a scoping study that is
used for the relative ranking of scenarios and thus requires
less accuracy on an absolute basis. Phase II is a very
detailed study that requires a much greater level of
accuracy.
Question 5: Is the capital cost and operating
estimates to be presented in year 2008 only or escalated for
n years? Will escalation parameters be provided to
successful bidder or assumptions will be made?
Answer to Question 5: Present all costs in 2008 dollars.
Question 6: Is the evaluation of cooling options (Task
5) to be conducted for both “Hybrid” and “Backyard”
re-powering?
Answer to Question 6: Yes
Question 7: Task 2 indicated re-utilization of STG
with existing or new condensers. Is the condition and
upgrade assessment of existing condensers and cooling system
to be included in the study?
Answer to Question 7: Yes. KeySpan will provide
available plant condition assessment data to support this
effort.
Question 8: Is there any reference soil
contamination/remediation, asbestos remediation/removal
studies available for both stations or these studies to be
included in re-powering study?
Answer to Question 8: Specific studies have not been
performed, however, information is available and will be
provided that should be factored into the studies.
Generally, insulation is to be assumed to be asbestos.
Question 9: Is it assumed that all steam turbines in
both Northport and Port Jefferson stations available for
hybrid re-powering for Phase I re-powering? What is the
general condition of the STG? (operating, retired, etc.)?
Answer to Question 9: Northport Units 1-4 and Port
Jefferson Units 3 & 4 are all operating and are generally in
good condition. The Northport Units 1-4 and Port Jefferson
Units 3 & 4 steam turbine generators are to be included in
the Hybrid re-powering study. Also, Northport Units 1-4 will
be retrofitted with GE “Dense Pack” HP/IP turbine
modifications over the next five years (2009 to 2012) to
improve efficiency.
Question 10: What is the area footprint limit of both
“Hybrid” and “Backyard” re-powering for both stations?
Answer to Question 10: The entire site is to be
considered available in the Phase I study to maximize
megawatt output.
Question 11: Is there any preference on the
type/model/manufacturer of heavy duty combustion turbine? Is
comparison/analysis of various types/models/manufacturers
required?
Answer to Question 11: A decision has not been made and
input from the successful bidder is requested. Past
re-powering studies have used the GE 7FA, but other electric
system planning expansion studies have used the Siemens G
machine.
Question 12: Is there any steam turbine condition
assessment/ upgrade study previously conducted to support
the re-powering study of 2002 (by LG)? Will this report be
made available to successful bidder for reference?
Answer to Question 12: No specific studies were done.
However we do have steam turbine generator condition
assessment information from past overhauls available for the
study.
Question 13: Any implementation phasing requirements
to be considered for both re-powering options?
Answer to Question 13: The Integrated Electric Resource
Planning study work performed by LIPA Planning will define
the timing requirements for system expansion that will be
factored into the study.
Question 14: Is the power block equipment to be
located indoors for both options?
Answer to Question 14: Yes
Question 15: What is the water treatment requirement
to be considered for study (part of the re-powered plant or
third party supply)? Is the assessment of de-mineralized
water source/type included in the study?
Answer to Question 15: A new demin system is to be assumed
required for each site. Northport has a new RO/EDI system
that may be reused.
Question 16: Task 2 stated that certain supporting
site facilities may be re-used in the design. Is the
condition, adaptability, relocation assessment of these
facilities to be included in the re-powering study?
Answer to Question 16: Yes
Question 17: Do we need to consider multiple
distillate fuels (no. 2, low sulfur, ultra low sulfur)?
Answer to Question 17: This will be determined by the
air quality study significant impact levels (generally low
sulfur 0.05 % S or less).
Question 18: Does our study price have to include the
cost of a physical inspection, life assessment and
recommendation of upgrades or will it be paid by Keyspan/LIPA?
Can it be a later adder to the contract?
Answer to Question 18: Life assessment shall be included
in your base work scope.
Question 19: For the backup liquid distillate fuel
supporting studies, is barge delivery to be assumed at the
site? Do we have to consider any changes to the offshore
delivery at Northport?
Answer to Question 19: An assessment of the fuel
unloading systems is to be included for both sites. Both
Northport and Port Jefferson have barge unloading
facilities. Conversion to accommodate distillate fuel
storage and delivery is part of the study scope.
Question 20: Will costs for the SIS be provided to us
during the study? Is SIS to be considered for new CC plants?
Answer to Question 20: KeySpan will share our limited SIS
cost information for your review and assessment for use in
the study (on a confidential basis with permission from the
patent holder). An independent feasibility evaluation and
conceptual layout is required for each site. Also, a cooling
tower study is available for Northport.
Question 21: Please confirm that electrical
transmission upgrades and costs associated with re-powering
or a new CC plant will be provided. Any necessary upgrades
to the LIPA owned substations are by proposer?
Answer to Question 21: LIPA planning will provide the
transmission upgrade requirements and cost estimates as well
as the associated substation upgrades. The Contractor shall
determine the plant electrical design and allow for
substation expansion space requirements.
Question 22: Provide the steam inlet conditions for
all turbines to be re-powered.
Answer to Question 22: Northport Units 1-4 are 2,373,000
lbs/hr at 1000F and 2400 psig
Port Jefferson Units 3 & 4 are 1,200,000 lbs/hr at 1000F and
1800 psig.
Question 23: Are site plans available in CAD?
Answer to Question 23: More detailed site plans will be
made available to the successful bidder.
Question 24: Are the LM6000 units at Port Jefferson
included in the re-powering study?
Answer to Question 24: Not directly. These units are
independent but share some common facilities such as the gas
supply that needs to be taken into account.
Question 25: When were the two units at Port Jefferson
mothballed? Is it the intent to include these units in the
re-powering studies?
Answer to Question 25: Units 1 and 2 are not to be
re-powered but are candidates for demolition to support
re-powering of Units 3 & 4. They have been mothballed for
about a decade.
Question 26: What is the current gas supply capacity
at each site (i.e., line size, pressure and flow). Is there
additional capacity available?
Answer to Question 26: Northport is supplied by the
Iroquois gas main. Port Jefferson is supplied by a 16 inch
diameter 350 psi KeySpan gas pipe. Part of the re-powering
study is for KeySpan and Iroquois to supply the
reinforcement requirements and costs to support the various
identified re-powering scenarios.
Question 27: Does KeySpan have a minimum per station
MW output target after re-powering?
Answer to Question 27: No
Question 28: Article 9.2, page 13, bullet 3: states
that “no more than four (4) additional pages of relevant
project descriptions and other qualifications material” may
be provided. “In addition, describe three (3) projects
similar to the one requested in this RFP”. Are the three
projects similar to be included in the four pages of project
descriptions or in addition to the four pages of project
descriptions? If they are in addition to, what is the page
limit for the three projects?
Answer to Question 28: Page limits referenced in Section
9.2 (third bullet) were meant to apply to relevant project
descriptions and other qualifications and do not apply to
the description of the three (3) projects similar to the one
requested in the RFP.
